Work to Create New Boxes Continues at the Louis II Stadium

Work to create new boxes at the Louis II Stadium is continuing, with the installation of two external lifts on the Avenue des Castelans and a footway along the facade.

This work will begin in the coming days with the installation of the metal structure for the lift towers.  Each tower will be divided into three pre-assembled sections, which will be transported to the site and assembled using a mobile crane.

When the metal structure is completed, the glazed facades will be assembled, forming an enclosed covered space.  Once the project is finished, the two lifts will be installed.

This will be followed at the beginning of May by the installation of the structure for the connecting footway, which will run along the facade of the Stadium.

These new boxes will be completed in time for the Herculis Meeting, to be held on 12 July 2019.